Detected on Saturday 14 November, 17h00
Dijon: a developer seeks compensation after refusal of a building permit
The City of Dijon refused a building permit three times to SCI JPLA; after a favorable ruling by the Lyon Court of Appeal in 2023, the developer is asking the administrative court for compensation for lost earnings.
In brief
Justice event (severity: low) in Dijon (Côte-d'Or), first detected on 14 November 2026 at 17:00. Reported by 1 source (1 article), last updated on 14 November 2026 at 17:00.
Dijon
Photo Christophe.Finot · CC BY-SA 2.5 · Wikimedia Commons- Category
- Justice
- Severity
- Low
- Place
- 21 Côte-d'OrDijon
- Detected
- 14 Nov, 17h00
- Updated
- 14 Nov, 17h00
- Reference
- no.19868
1 article · 1 source · 1 bord sur 3 · outlets: left 0, centre 1, right 0
Angle comparison
A comparison is written as soon as the event is covered by at least two sides (left, centre, right).
Lire les sources · 1 article, 1 source
- 17h00Le Bien PublicCentreWire14 NovDijon. Après la cour d’appel de Lyon, ce projet immobilier de nouveau devant le tribunal administratif
La Ville de Dijon avait refusé à trois reprises d’accorder un permis de construire à la société civile immobilière (SCI) JPLA. En 2023, la cour d’appel avait rendu un jugement en faveur du promoteur. Aujourd’hui, ce dernier demande une indemnisation au titre du manque à gagner.